November 5, 2026
The City of Belvedere's latest schedule has the Beach Road seawall project finishing by November 25. The city's encroachment and road-closure list, dated October 22, has a PG&E gas-leak repair permit at 67 Beach Road starting November 16. That is nine days before the forecast finish.
Since late July, the work on Belvedere's front door has been one large project with one contractor on one stretch of shoreline. This winter the work changes shape. It becomes a series of small utility permits spread across Beach Road, West Shore Road, Peninsula Road and Windward Road, and several of them run to mid-March 2027.
The project is a structural one. Crews are driving steel sheet piles along the seawall from the intersection of Beach Road and Main Road to Beach Road and Peninsula Road. In its project FAQ, the city says erosion has been undermining the wall. The piles are meant to stabilize it, give the wall and the roadway seismic support, and protect Beach Road and the homes beside it.
Construction was scheduled for July 27 through October 30, 2026. PG&E and Comcast went first, moving their communications, electric and gas lines out of the way. MMWD installed a temporary shut-off valve for the water lateral. The contractor put a turbidity curtain in the water and set up vibration and settlement monitoring on land. According to the city's August 18 update, the first phase meant digging inside Beach Road, with single-lane traffic and flaggers during work hours.
The piles are big. On October 7, Public Works Director Antony Boyd told the Beach Road Stabilization Project Oversight Subcommittee that crews had started installing 42-foot steel sheet piles along the shoreline, The Ark reported. In the same Ark story he described the schedule this way:
"There have been delays, and it definitely looks like it will be going into November to complete the work."
On October 19, the city named the cause. It said very unfavorable tides and high water had forced the contractor, Gordon N. Ball, to rearrange its work so it could meet the October 30 deadline for in-water work. The city added that it would file for extensions if needed.
The order of the remaining work matters for anyone walking or parking on Beach Road. The October 19 update says the in-water work comes first. After that, crews move to the land side, connecting the steel piles and then repairing and replacing the roadway and sidewalks. The full project is forecast to be finished by November 25. That date is the city's current schedule, not a promise, and it could still move.
When it does finish, two things come back:
Because the sidewalk and roadway repairs come at the very end of the sequence, the walking route will be among the last things to reopen.
The city publishes its encroachment and road-closure list as a dated document. The October 22 edition shows the next layer of work. Most of the new entries are PG&E permits to find and dig up gas leaks, and several fall on or near the seawall corridor.
| Address | Permit window | Work listed |
|---|---|---|
| 10 Windward Road | Nov 9, 2026 to Mar 9, 2027 | PG&E gas-leak repair |
| 67 Beach Road | Nov 16, 2026 to Feb 16, 2027 | PG&E gas-leak repair |
| 16 Mallard Road | Dec 7 to Dec 10, 2026 | PG&E gas service line installation |
| 100 Beach Road | Dec 8, 2026 to Mar 8, 2027 | PG&E gas-leak repair |
| 35 West Shore Road | Dec 8, 2026 to Mar 8, 2027 | PG&E gas-leak repair |
| 57 Peninsula Road | Dec 8, 2026 to Mar 8, 2027 | PG&E gas-leak repair |
| 7 Beach Road | Dec 16, 2026 to Mar 16, 2027 | PG&E gas-leak repair |
| 31 West Shore Road | Dec 22, 2026 to Mar 22, 2027 | PG&E gas-leak repair |
| 2 Cove Road | Sep 18, 2026 to Mar 18, 2027 | PG&E underground cable upgrade and pad-mount transformer, with a 55-foot trench |
These are permit windows, not work days. The list gives the period during which PG&E may work at each address. It does not say how many days a crew will actually be there. All of these are listed as encroachments, not road closures, and the same list labels the jobs that shut a street separately as road closures.
Put together, the windows have a pattern. Beach Road has three separate gas-leak permits, at 7, 67 and 100 Beach Road. West Shore, Peninsula and Windward have four more. Most of them stay open into March, and the last one, at 31 West Shore Road, runs to March 22. The seawall had one site and one end date. This work is spread over at least eight addresses, and the dates are staggered.
Two items on the October 22 list are true road closures, both for PG&E gas-leak repairs:
The second date is notable. The same list shows a full closure of Belvedere Avenue from No. 49 to Belvedere Way on October 29, from 9 a.m. to 4:30 p.m., for a two-inch grind and asphalt overlay, with detour signs and temporary asphalt ramps at the transitions. A separate permit for October 28 through 30 covered dig-out repairs at 18 locations. Those used one-lane reversible flagging on Belvedere Avenue from No. 298 to Pine Avenue and on West Shore Road from No. 50 to the end. Seven weeks after that repaving, PG&E is scheduled to dig at 49 Belvedere Avenue, the address where the overlay began.
The rest of the list is smaller jobs that don't close streets. AT&T has conduit repair permits at 10 and 30 San Rafael Avenue through December 30 and December 28. It has a boring and hand-dig permit at 1 Bellevue Avenue through January 25, 2027, and excavation at 4 Blanding Lane through December 7. That last permit carries the city's standard condition that at least 10 feet of paved road stay clear for passing vehicles.
If the November 25 forecast holds, the reopened seawall sidewalk will get its first real use during the holiday run between Belvedere Cove and Tiburon's Main Street. The PG&E windows at 100 Beach Road and 7 Beach Road open around the same time.
Over the same weeks, the ferry at the Tiburon end of the walk switches to a winter schedule. For November and December 2026, the Angel Island Tiburon Ferry runs no service Monday and Tuesday and no regularly scheduled service Wednesday through Friday. On weekends it leaves Tiburon at 10 a.m., 11 a.m. and 1 p.m., plus a 3 p.m. boat for campers only. It also runs those departures on Veterans Day, November 11, and on the day after Thanksgiving, November 27. The operator says the schedule can change without notice.
Back on Beach Road, the 67 Beach Road window closes February 16. The ones at 100 Beach Road and 7 Beach Road stay open until March 8 and March 16. Those dates, not November 25, mark the end of Beach Road's construction season.
At First California Realty, we track Belvedere's permit lists and project updates the way we track sales, because they shape daily life on these streets. If one of the winter work windows overlaps your plans for a property on Beach Road or the lagoon streets, let's connect. A confidential conversation, starting with a home valuation, is an easy first step.